Open questions

What CORA needs the 8.3.2 team to confirm before the model can be trusted.

8.3.2 was reverse-engineered from ALS's public facility pages (als.lbl.gov/beamlines/8-3-2, microct.lbl.gov) and the public als-computing GitHub org, not from a live connection. The device structure is read from the DXchange / DXfile HDF5 data record that the ALS tooling reads, but ALS runs BCS (a LabVIEW Beamline Control System, not EPICS) and publishes no per-beamline channel manifest, so the Inventory is a planned shape with control handles unbound. This is CORA's first ALS Site and its first BCS / LabVIEW controls house-style. Each row below is a fact the beamline team owns, not a CORA modelling choice (those are on Model). It is a delete-on-answer queue. Priorities are Blocks-build, Blocks-go-live, and Nice-to-have.

Topology and scope

ID Priority Question CORA assumes Resolves
ENC-1 Blocks-go-live The hutch grouping: a single experiment hutch, or a separate optics hutch feeding it? A single 8-3-2-hutch. The Enclosure grouping.
SRC-1 Nice-to-have The Superbend field and critical energy. A superconducting bending-magnet source, 6-43 keV; field pending. The source Asset detail.
ALSU-1 Nice-to-have The ALS-U upgrade fate of 8.3.2: does it go dark, get rebuilt, or relocate, and on what schedule? Dark time no sooner than October 2027; 8.3.2's fate carried pending. The deployment roadmap.

Source and optics

ID Priority Question CORA assumes Resolves
MACHINE-1 Nice-to-have The ALS storage-ring state 8.3.2 reads (the source_name / current handles). Observe-only machine state, a loose StorageRing; exact handles pending. The machine-state observation.
MONO-1 Blocks-go-live The energy optic: the mechanism (multilayer vs crystal), d-spacing, and how the energy, Z2, turret1 / turret2, and TC2 / TC3 channels relate. An energy-setting Monochromator, 6-43 keV; energy the master axis. The monochromator and energy modelling.
OPT-2 Nice-to-have The slit blade-axis map (the hslits_* and vslits_* channels) and handles. Horizontal + vertical slits bound to Slit. The slit Asset detail.
FILT-1 Nice-to-have The attenuating-filter materials and thicknesses on the filter_y axis. A filter bound to Filter. The filter Asset detail.

Sample endstation

ID Priority Question CORA assumes Resolves
SAMPLE-1 Blocks-go-live The sample-motor stack: the rotary, the sample-centring axes (sample_x / sample_y), and the role of axis1pos / axis2pos / axis5pos. A RotaryStage plus a LinearStage; axis sets and models pending. The sample-stage modelling.
ROT-1 Blocks-go-live Which sample-stack axis is the tomographic rotation. One of the axisNpos channels is the rotation; identity pending. The rotation Asset binding.
TRIG-1 Nice-to-have The triggering / synchronization scheme for continuous-rotation tomography. The rotary stage is the master clock feeding the camera trigger. The trigger wiring.

The detector

ID Priority Question CORA assumes Resolves
DET-1 Blocks-go-live The detector chain: the camera sensor / frame rate / model, the scintillator_type, and the camera_objective set. A Scintillator + Objective + Camera; specs are per-dataset values, model carried pending. The detector modelling.
DET-2 Nice-to-have The detector-stack axes (camera_distance, camera_elevation, tilt_motor): models, travels, and which is the propagation distance. A LinearStage detector stack; camera_distance the propagation distance. The detector-stack modelling.

Control and safety

ID Priority Question CORA assumes Resolves
CTRL-1 Blocks-build The BCS / LabVIEW control handles per 8.3.2 device (absent from any public manifest). The handles are unbound, carried pending; the control plane is ALS BCS. Binding each Asset's control handle.
PSS-1 Blocks-go-live The ALS personnel-safety permit signals and the photon / front-end shutters (not published per beamline). Permit leaves and shutters to be named; not invented here. The Enclosure permit signals and the safety tier.
SUP-1 Nice-to-have The vacuum extent and the cooling-water / beam / power supplies. Photon beam, cooling water, vacuum, and power. The Supply observations.
GOV-1 Nice-to-have The ALS operator pool and safety-review structure (site-level). Carried pending on the ALS Site, not instantiated per beamline. The governance principals.